Coachella Broke Ground on the Avenue 50 Bridge. The Old Low-Water Crossing Stays Open Until It's Done.

November 12, 2026

When the next big storm comes through the east valley, which Avenue 50 will drivers be on? It will be the old one. Coachella broke ground on its new Avenue 50 bridge on Thursday, October 15, 2026, at Sierra Vista Park. Mayor Frank Figueroa, city councilmembers, regional transportation representatives and community leaders were there, KESQ reported. The bridge will take years to build. Until it opens, the low-water crossing through the Coachella Valley Stormwater Channel is still the road, and it still floods.

That arrangement is intentional, and it explains most of what drivers and CV Link riders will see between now and the end of the project.

Six hundred feet is the whole plan

The new bridge is not going in on top of the current road. City Engineer and Public Works Director Andrew Simmons told KESQ that it will be built about 600 feet south of the existing crossing. That way crews can build the new roadway without shutting the old one for the length of construction.

"The main thing just for the community to remember is that Avenue 50 low-water crossing will remain open during the construction," Simmons said, as reported by KESQ.

The city also plans to repave the existing crossing to keep traffic impacts down during construction. So the road from Coachella to Expressway 86 should drive a little better this winter than it did last winter. It will also flood exactly as it always has. In the same report, KESQ noted that the crossing may still face weather-related restrictions when the channel runs.

Moving the alignment south keeps Avenue 50 open every dry day of construction. It does nothing for the wet days until the new span carries traffic.

What the dip does when the channel runs

Councilmember Juan Martinez and the mayor both described the bridge in terms of reliability. Martinez stressed better access for emergency vehicles. Figueroa, who KESQ reported uses Avenue 50 to commute, called the current road a hurdle for drivers trying to reach Expressway 86.

Recent storms show why. During Tropical Storm Hilary, The Desert Sun's August 21, 2023 update put Avenue 50 at the Whitewater Wash on its list of Coachella closures. Less than two weeks later came a storm on Friday, September 1. KESQ reported that Avenue 50 at the Whitewater Channel was still closed on Sunday afternoon, the only Coachella crossing that hadn't reopened.

So the issue isn't only that the crossing closes. It's often the last one to reopen. Other streets drain and clear while this one waits for the channel to drop and for crews to clear what the water left behind. The bridge is meant to end that pattern. The 600-foot offset means the pattern runs as usual until the bridge is finished.

Twelve years to a groundbreaking

Anyone who has heard about this bridge for a decade is right. The September 21, 2026 city staff report lays out the timeline:

  1. 2014: The city wins federal Highway Bridge Program funding for environmental review, right-of-way, design and construction.
  2. 2019: Environmental review is finished, and design and right-of-way work are authorized.
  3. 2025: Right-of-way acquisition is complete and certified.
  4. May 2026: Caltrans authorizes construction after approving the final design.
  5. July 9, 2026: Bids are invited, with a mandatory job walk on July 28.
  6. September 3, 2026: Seven companies submit bids.
  7. October 15, 2026: Groundbreaking at Sierra Vista Park.

KESQ's account explains why the middle years took so long. Simmons said the project needed the City of Coachella, the Cabazon Band of Indians, the Coachella Valley Water District and Caltrans to work together, because each has interests or jurisdiction in the area. The city also went through eminent domain to secure land for construction. Building 600 feet south meant acquiring land for a new alignment, and acquiring land takes years.

Who is building it, and who is paying

Riverside Construction Company of Riverside submitted the lowest of seven bids at $48,709,821.10. Ames Construction came in at $50.4 million, and Steve P. Rados was highest at $60.8 million. With a 10% contingency, the construction budget comes to $53,580,803.21. Most of the money comes from outside Coachella:

Funding source Construction allocation
Highway Bridge Program $42,241,089.23
CVAG $8,784,140.61
Measure A $1,600,000.00
SB1 $555,573.37
City water fund $400,000.00
Total $53,580,803.21

A separate construction-management contract adds $7,970,641, and the Highway Bridge Program covers most of that too. The federal share is the reason the city held onto a project that took twelve years to reach construction.

The scope goes well beyond the span. The staff report describes realigning Avenue 50 and widening it from two lanes to a six-lane major arterial. It also covers realigning Tyler Street, waterline work, a new traffic signal, street lighting and pedestrian improvements. A planned interchange at Expressway 86 and Avenue 50 is a separate second phase and is not part of this contract.

The clock, and the path that closes

The contract gives the builder 550 working days after the notice to proceed. City officials told KESQ to expect about two years, and the CV Link construction updates page gives 2028 for completion. Two winters and two monsoon seasons fall inside that window.

The project affects cyclists as well. The same CV Link page says the path at Avenue 50 will be closed for the duration of the project, with a detour posted around the construction zone. For riders using the stretch between La Quinta and Coachella, the Avenue 50 crossing of the path is the segment the bridge work takes out of service.

Drivers will mostly feel construction as work-zone traffic. City officials asked drivers in the KESQ report to stay alert near construction, follow posted signs and watch for crews near the road.

The payoff the city describes is larger than the crossing itself. Officials expect better links between Expressway 86, industrial areas near Avenue 52 and downtown Coachella. Simmons also connected the work to the planned passenger rail service between Los Angeles and Coachella, with Coachella in line for a station.

Hearing about a closure before you reach the water

The crossing's storm behavior hasn't changed, so the useful step this winter is getting closure news early. Coachella and Riverside County each run an alert channel, and the city lists a direct line:

  • City of Coachella SMS Alert System: The city runs it with Regroup. Text "Join alerta" to 31002 to subscribe, as described on the city's alerts page.
  • Alert RivCo: The county system covers floods and severe weather. Mobile and VoIP numbers have to be registered, and email can be added; details are on the Riverside County Emergency Management page.
  • Flooding and signal concerns: The city's emergency management page lists 760-501-8100.

Until the new span opens 600 feet south, a flooded Whitewater Channel still means a closed Avenue 50, and these alerts are the quickest way to find out.

Large public projects like this one affect commutes, nearby land and the value of property along the corridor. Robert Andrew Millar & Associates follows the Avenue 50 corridor closely. If you want to talk through what the bridge and the planned interchange could mean for property you own or are considering in the east valley, schedule a confidential consultation.